Consultation Process – Main Milestones
The views and concerns of the stakeholders are important
to TOTAL E&P UK and our aim is to be fair and open
throughout the whole of the MCP-01 decommissioning
process.
Our core values focus on professionalism, respect
for employees, an ongoing concern for safety and environmental
protection, and a commitment to contribute to the development
of local communities.
May 2006 – OSPAR Consultation on MCP-01 Concrete Substructure
The UK Department of Trade and Industry and the Norwegian Ministry of Petroleum and Energy notified in separate letters the OSPAR Secretariat that they are considering issuing a permit, under paragraph 3b of OSPAR Decision 98/3, allowing for the MCP-01 concrete substructure to be left in place at its present location.
For this consultation the document MCP-01 Concrete Substructure – An Assessment of Proposals for the Disposal of the Concrete Substructure of Disused MCP-01 Installation, dated 10 February 2006, has been submitted to the OSPAR Secretariat.
February 2006 – Third Draft of MCP-01 Decommissioning Programme
A Third Draft of the MCP-01 Decommissioning Programme was prepared after the statutory consultation on the Second Draft in 2005 with the inclusion of the stakeholders responses.
The Third Draft has been further updated in February 2006 to reflect present plans for offshore works and has been made available on this web site for the OSPAR consultation.
March 2005 – Statutory Consultation on MCP-01 Decommissioning programme
With the Public
Notice in
UK newspapers and journals
the public was notified about
the initiation of the Statutory
Consultation of MCP-01 Decommissioning
Programme on 9th March 2005
lasting to 25th April 2005.
May 2004 – Stakeholder round
table discussion
In May 2004, an informal stakeholder round table discussion
was held with some of the key stakeholder group representatives.
The meeting had two primary objectives:
- To review decommissioning issues in the light
of the knowledge gained since the Frigg stakeholder
workshop in September 2000
- To gather from participants their reflections on
decommissioning MCP-01 based on preliminary findings
of studies commissioned
by TOTAL E&P UK into the different aspects of decommissioning
MCP-01
The meeting was chaired by independent facilitator,
Andrew Acland (Dialogue by Design), with the aim of
maintaining a fair and open process.
A record of the meeting will be included in the Decommissioning
Programme during the public consultation.
January 2004 – Consultation of Scope of Work
for the EIA
The MCP-01 decommissioning consultation process started
with an invitation to comment on the Proposed
Scope of Work for the Environmental Impact Assessment
of
MCP-01 (EIA) sent out in January 2004. Though not a
requirement under UK law, this document is a good opportunity
of engaging stakeholders and seeking views at the earliest
opportunity. A Norwegian
translation is also available.
A Public
Announcement was also placed in a number
of key UK and international publications to ensure
that as wide an audience as possible was aware that
MCP-01 is being considered for decommissioning. Those
interested in participating in the consultation process
were urged to contact TOTAL E&P UK to ensure they
were included in the process.
Key Consultation milestones so far:
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
Date |
 |
 |
 |
Milestones |
 |
 |
 |
 |
 |
April 2006 |
 |
 |
 |
OSPAR Consultation |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
March
2005 |
 |
 |
 |
Statutory
Consultation |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
May
2004 |
 |
 |
 |
Key
stakeholder groups invited to roundtable discussion |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
March
2004 |
 |
 |
 |
Approval
of EIA programme by the Norwegian authorities |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
January/February
2004 |
 |
 |
 |
Consultation
on EIA document |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
January
2004 |
 |
 |
 |
Stakeholders
invited to comment on EIA scope of work |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
January
2004 |
 |
 |
 |
Letters,
information pack sent to stakeholders |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
January
2004 |
 |
 |
 |
MCP-01
dedicated internet site launched |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
January
2004 |
 |
 |
 |
Public
Announcement |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
March/April
2003 |
 |
 |
 |
Face
to face meetings with key stakeholders |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
This table will be updated as the consultation process progresses |